2023 Pavement Rehabilitation Project
The project is located on Buena Vista Avenue, Longfellow Road, and Monte Vista Avenue in the City of Mill Valley. The work generally consists of mobilization; setup and maintenance of a traffic control system; developing and implementing a water pollution control program; cold planing, removing and disposing of asphalt, concrete, base and/or native materials; placement of hot mix asphalt (HMA) and rubberized hot mix asphalt (RHMA); miscellaneous concrete construction; lowering and adjusting utility frames and covers; replacement of traffic striping, pavement markings and raised pavement markers; and cleanup of the project area.
2023 Pavement Rehabilitation Design Plans (PDF)
The heavy duty work of grinding and paving of all three street segments is complete.
Photos from the Week of June 5th: Work on Monte Vista, Buena Vista, & Longfellow
2023 Slurry Seal
The following streets received a slurry seal treatment this summer:
2023 Slurry Seal Streets and Limits (PDF)
The scope of work includes applying a thick protective coating to the approximate 50 streets included in the above list to improve their ridabiity and extend their life. This work includes, but is not limited to, implementation of storm water pollution and prevention; traffic control; applying asphalt slurry seal; applying striping, markers, crosswalks and legends; and all other work related to protecting the roadway surface and restoring the street striping, and installing new striping.
2023 Patch Paving Project
The 2023 Patch Paving Project repaired spot areas of asphalt pavement along various streets in the City in advance of the 2023 Slurry Seal project. This is a cost effective measure to improve the street without requiring an entire rehabilitation.
Patch Paving Project Locations (PDF)
This project started the week of May 2023, and is complete.